NEWS

 

PROJECT NEWS

 

Invercargill Airport Stage 2 Building Opens - 14 February 2016

 

The second stage of the Invercargill Airport Terminal Building opened for business at 6.00am on Sunday 14 February following a Maori Blessing by Ngai Tahu Kaumatua, Michael Skerrett.

 

The terminal building is now substantially complete, with the outstanding elements of removing temporary works and completion of remaining apron works due to be complete within March 2016.

Exterior shot of IAL Terminal Stage 2 building

 
Internal
 
Internal 2
   

 

Marine Parade Skyline Building, Queenstown - August 2015

 

This prime lakefront site adjacent to the famous Eichardts Hotel recently underwent significant ground improvement works involving the construction of a combined gravel and cement-stabilised raft foundation.

 

Construction of the prestigious commercial building has now commenced with works on the concrete raft foundation progressing over completed ground improvements.

 

The completed building will include a kitchen, restaurant, retail shop, offices, hotel suites and a luxuiry 2-bedroomed penthouse apartment.

 

 

Development of site adjacent to Eichardts
   

Glenorchy Market Place, Glenorchy - August 2015

 

Peak Projects have been engaged as Project Manager for this exciting development on the site of the previous Glenorchy Camp Ground.

 

It will be undertaken in two stages, with Stage 1 known as Camp Glenorchy being well through the design stage, but construction commencement has been delayed by a resource consent appeal being lodged.

 

Stage 2 of the development is still in the concept design stage.

 

Artist's impression of Glenorchy Camp Ground development
   

Clare House Rest Home & Retirement Village, Invercargill - August 2015

 

Peak Projects have been employed as Project Managers to manage the expansion of the existing Clare House Rest Home and Retirement Village in Invercargill.

 

Broken into 3 stages, the contract is a challenging one, extending the building footprint and upgrading existing facilities whilst minimising disruption and disturbance to the day-to-day running of the home, to visitors and to the surrounding neighbours.

 

Work commenced on site in July 2015 and the project has an anticipated completion date of August 2016.

 

Progress may be viewed on the time-lapse webcam at http://build.clarehouse.co.nz/

 

 

 

Artist's impression of Clare House porte cochere
   

Suffolk Street Affordable Housing Units, Arrowtown - August 2015

 

Engaged by Queenstown Lakes Community Housing Trust, Peak Projects are overseeing and managing the development of 10 residential rental houses in Arrowtown.

 

Stage One (units 1 - 4) was completed at the end of May 2015, with Stage Two works commencing concurrently and being completed by early December 2015 enabling full occupancy by Christmas.

 

Following the experience gained during the early dates of Stage 1, it was decided in discussions with the Client to proceed with Stage 2 on a "design-and-build basis" with the incumbent contractor.  Peak Projects have negotiated and managed the process from the outset.

 

Suffolk St cottage
   

Shotover Country Affordable Housing Civil and Building Works, Queenstown - August 2015

 

Peak Projects have been engaged by Queenstown Lakes Community Housing Trust (QLCHT) to project manage the consenting, design and construction of roading, utilities and titling lots for 44 residential units, within the Shotover Country subdivision.  Civil construction is due for completion in December 2015 with the first of 44 houses being started concurrnelty with, or slightly ahead of, finishing the civils work.

 

Peak Projects are presently assisting the TYrust to negotiate with and engage contractors for the design and build of the 44 houses.

 

Shotover Country Civil Construction
   

Felton Road Winery, Bannockburn, Central Otago - August 2015

 

Peak Projects have been appointed by the Felton Road Winery as project managers for the design and construction of a new subterranean barrel cellar and a substantial extension to the existing "front-of-house" facilities.  The two projects are being developed independently, but overlapping in time.

 

Design and contractor procurement for the cellar is now complete, earthworks have started and building will commence early in September with projected completion for December 2015.  The extension is presently going through design development with procurement and then construction due to be underway within the next few months.  Construction may need to be "staged" to suit the winery's on-going business, with a break during the summer months and completion following the 2016 harvest.

Felton Road excavation
   

Amisfield Winery - New Store, Lowburn, Central Otago - August 2015

 

Initially Peak Projects were engaged to provide design coordination and limited cost advice on a project that had already commenced.  Over the following few months, the role gradually expanded and PPIL were asked to take over the full project management of the development of a large insulated agricultural shed that was being relocated and architecturally modified to potentially fulfil the dual role of barrel and goods store.  The project is now under construction with completion envisaged for later this year.

 

Amisfield Lowburn Store Building construction